$11M project could triple weather monitoring stations, improve Missouri River flood control

$11M project could triple weather monitoring stations, improve Missouri River flood control

  • Updated
{{featured_button_text}}
2011 high water

The Fort Peck Dam spillway had only been used four years prior to 2011’s historic high water, which set a record. The U.S. Army Corps of Engineers is proposing to increase its network of weather gathering systems across the Upper Missouri River Basin to better predict runoff, especially of plains snowpack.

In an attempt to ensure better monitoring of precipitation across the Upper Missouri River Basin for flood control, the Army Corps of Engineers is studying the creation of a new network of weather stations.

“Certainly this type of thing is unique,” said climatologist Nathan Edwards, who oversees South Dakota’s network of weather stations. “It has a lot to do with three things contributing to flooding: saturated soils, frozen soils and snow. A lot of what this focuses on is soil moisture and snow monitoring.”

Test stations for proof of concept are being upgraded in Bozeman at the Montana State University campus; in Sheridan, Wyoming; and in Brookings, South Dakota. Once the systems and equipment have demonstrated their capability, the Corps is proposing to install 360 similar stations at a cost of more than $31,000 apiece.

The details of the study and proposed network are contained in a draft environmental assessment for updating the three soil moisture and plains snowpack monitoring stations.

Photo op

Scott Wilemon takes pictures of the Fork Peck Dam spillway in 2011 as the water released from Fort Peck Reservoir ran at a historic high.

2011 reaction

The proposed update and expansion of the monitoring network was triggered by the 2011 flood on the Missouri River, a record-shattering spring that saw the “largest volume of flood waters since the initiation of record-keeping in the 19th century,” according to the U.S. Geological Survey. “The high levels of runoff from both snowpack and rainfall stressed the Reservoir System’s capacity to control flood waters and caused massive damage and disruption along the river.”

The reservoir system is made up of six dams, including Fort Peck Dam in Montana, as well as Lake Sakakawea (Garrison Dam) just across the border in North Dakota. In 2011 the dams dealt with 61 million acre feet of runoff. Last year the system confronted another high water year with 60.9 MAF of runoff, the second highest in 122 years of record keeping.

“Following the 2011 flood event on the Missouri River, the Corps and an Independent Review Team comprised of academic expertise and officials from various federal agencies, determined that the Corps substantially underestimated the wet soil conditions in the plains and the plains snowpack in its water supply forecasts,” according to the EA.

“Typically the (existing) stations don’t measure frozen precipitation,” Edwards said.

There are about 180 existing sites that collect weather data for the Upper Missouri River Basin. Adding another 360 sites across five states — the other two states are North Dakota and Nebraska — would “provide the necessary quality of data to better inform runoff forecasting,” the EA stated. In addition, 30 of the existing 180 sites would be retrofitted with new equipment.

Edwards said each state would analyze the data from its network of weather stations before passing it on to the National Oceanic and Atmospheric Administration. The federal agency would run the data through its weather models to create snow water equivalent estimates to be passed on to the Missouri River Basin forecasting center.

Swimming in the picnic area

Mike, Ray and Joe Guza, along with Doug Long, take a swim in Fort Peck Reservoir at Milroy's Cove in 2011. Flooded by record high water, a shade shelter poked above the lake 30 yards from shore.

Testing

Last year at South Dakota State University Edwards and his colleague tested different instruments and measurement techniques to find the best equipment for installation at the test sites in Bozeman and Sheridan.

The MSU facility will “require the installation of an entirely new monitoring station as no station currently exists.” The existing University of Wyoming station near Sheridan has soil moisture sensors but needs other equipment to bring it up to standards.

In addition to the proposed sites, the EA said the restoration and maintenance of snowpack monitoring sites, such as SNOTEL, and streamflow gauges would also be imperative.

In 2013 to save money the USGS planned to shut down some of its streamflow gauges in Montana, but the state stepped in to keep them running.

One of the most difficult measurements the climatologists have wrestled with in designing the stations has been measuring the amount of moisture in snowfall. The most accurate method is to have a person measure the snow depth at several locations, since snow depth can vary.

Without manual measurements the next best system was to use stakes and sonic snow depth sensors at several spots around a site. Cameras will be installed as backups to the sonic sensors.

For all

Constructing the new network of stations would not only benefit the Army Corps of Engineers for its flood forecasting and management, the agency stated, but would also be available to other local, state and federal agencies for drought monitoring, water supply forecasts and fire hazard reporting.

“With an increase in quality and quantity of data, managers may better forecast and offset potential flooding events.”

The U.S. Army Corps of Engineers isn’t predicting a heavy runoff this spring at 36.3 MAF, almost half of the record-setting 2011 spring flow, but that prediction is complicated by the fact that much of the Upper Missouri River Basin already has soil moisture levels well above normal.

“Generally, when soil moisture is high during the winter, the potential for high March-April runoff is much higher,” according to the Corps’ January forecast. How high runoff will be in March and April will “depend greatly on the accumulation of plains snowpack over the next two to three months.”

The public can comment on the draft EA, which is available at: https://www.nwo.usace.army.mil/Missions/Civil-Works/Planning/Project-Reports/. Comments can be mailed to: U.S. Army Corps of Engineers, Omaha District; CENWO-PMA-C; ATTN: Rebecca Podkowka; 1616 Capitol Ave.; Omaha, NE 68102-4901. Comments can also be emailed to: cenwo-planning@usace.army.mil. Mail must be postmarked or received no later than Feb. 10.


Eastern Montana flooding

Gazette photo editor took these aerial photos of flooding in Eastern Montana.

You must be logged in to react.
Click any reaction to login.
0
0
0
0
0

Be the first to know

* I understand and agree that registration on or use of this site constitutes agreement to its user agreement and privacy policy.

Related to this story

Most Popular

Get up-to-the-minute news sent straight to your device.

Topics

News Alert

Breaking News